Do you know why you need to read this website and exactly what the relationship to checking out publication Earned Value Management Using Microsoft Office Project: A Guide For Managing Any Size Project Effectively, By Sham Dayal In this contemporary period, there are many methods to get the publication and also they will certainly be a lot easier to do. One of them is by getting guide Earned Value Management Using Microsoft Office Project: A Guide For Managing Any Size Project Effectively, By Sham Dayal by on-line as just what we inform in the web link download. Guide Earned Value Management Using Microsoft Office Project: A Guide For Managing Any Size Project Effectively, By Sham Dayal can be an option considering that it is so correct to your need now. To obtain the book on-line is very easy by simply downloading them. With this opportunity, you can check out guide wherever as well as whenever you are. When taking a train, waiting for checklist, and awaiting somebody or various other, you can read this on the internet e-book Earned Value Management Using Microsoft Office Project: A Guide For Managing Any Size Project Effectively, By Sham Dayal as a buddy again.

Earned Value Management Using Microsoft Office Project: A Guide for Managing Any Size Project Effectively, by Sham Dayal

PDF Ebook Earned Value Management Using Microsoft Office Project: A Guide for Managing Any Size Project Effectively, by Sham Dayal
Earned Value Management Using Microsoft Office Project: A Guide For Managing Any Size Project Effectively, By Sham Dayal. In undertaking this life, lots of people always aim to do as well as get the very best. New expertise, experience, session, and everything that can enhance the life will certainly be done. Nevertheless, lots of people occasionally feel puzzled to obtain those things. Really feeling the limited of encounter and also sources to be far better is one of the lacks to own. Nevertheless, there is a very basic point that can be done. This is what your teacher consistently manoeuvres you to do this one. Yeah, reading is the solution. Checking out a publication as this Earned Value Management Using Microsoft Office Project: A Guide For Managing Any Size Project Effectively, By Sham Dayal and also other recommendations could enrich your life high quality. Just how can it be?
This Earned Value Management Using Microsoft Office Project: A Guide For Managing Any Size Project Effectively, By Sham Dayal is extremely proper for you as beginner viewers. The readers will certainly consistently begin their reading routine with the preferred theme. They might rule out the author and also author that produce guide. This is why, this book Earned Value Management Using Microsoft Office Project: A Guide For Managing Any Size Project Effectively, By Sham Dayal is actually appropriate to review. However, the principle that is given up this book Earned Value Management Using Microsoft Office Project: A Guide For Managing Any Size Project Effectively, By Sham Dayal will certainly reveal you several things. You could begin to love additionally reviewing until the end of the book Earned Value Management Using Microsoft Office Project: A Guide For Managing Any Size Project Effectively, By Sham Dayal.
Additionally, we will share you guide Earned Value Management Using Microsoft Office Project: A Guide For Managing Any Size Project Effectively, By Sham Dayal in soft file kinds. It will certainly not disturb you making heavy of you bag. You require only computer gadget or gadget. The link that we provide in this website is readily available to click and afterwards download this Earned Value Management Using Microsoft Office Project: A Guide For Managing Any Size Project Effectively, By Sham Dayal You know, having soft data of a book Earned Value Management Using Microsoft Office Project: A Guide For Managing Any Size Project Effectively, By Sham Dayal to be in your device can make relieve the visitors. So in this manner, be an excellent visitor now!
Simply connect to the web to gain this book Earned Value Management Using Microsoft Office Project: A Guide For Managing Any Size Project Effectively, By Sham Dayal This is why we suggest you to use and also utilize the developed innovation. Reading book does not suggest to bring the published Earned Value Management Using Microsoft Office Project: A Guide For Managing Any Size Project Effectively, By Sham Dayal Developed technology has permitted you to review just the soft documents of guide Earned Value Management Using Microsoft Office Project: A Guide For Managing Any Size Project Effectively, By Sham Dayal It is very same. You might not have to go and get conventionally in browsing the book Earned Value Management Using Microsoft Office Project: A Guide For Managing Any Size Project Effectively, By Sham Dayal You may not have adequate time to invest, may you? This is why we provide you the most effective means to get the book Earned Value Management Using Microsoft Office Project: A Guide For Managing Any Size Project Effectively, By Sham Dayal now!

This invaluable reference effectively combines earned value management (EVM), the most widely accepted cost management technique, with the most widely used scheduling tool, Microsoft Office Project. It is a practical guide to end-to-end scheduling and cost management and includes a six-month trial version of a unique EVM software tool that will enable you to more effectively manage your projects, track and report the status and progress of projects, and take necessary action before projects fail. Supported with practical examples, this guide demonstrates how EVM can be effectively applied to any size project or program with the same rigor as that of a large or critical project or program.
KEY FEATURES
- Includes a unique EVM software tool that will save you substantial time and effort so you can focus on the actual management of projects or programs
- Covers the knowledge areas of schedule and cost management and is aligned with the Practice Standard for Earned Value Management published by PMI
- Provides a practical step-by-step approach to building a schedule quickly and contains efficient EVM cost management techniques using Microsoft Office Project to manage projects throughout their entire life cycle
- WAV offers free downloadable Excel tables with defined formulas for EVM calculations, a project schedule created using EVM and Microsoft Office Project, an EVM slide presentation, and an EVM software user manual -- available from the Web Added Value Download Resource Center at jrosspub.com
- Sales Rank: #1333840 in Books
- Published on: 2008-09-26
- Original language: English
- Number of items: 1
- Dimensions: 9.50" h x 7.50" w x .50" l, .99 pounds
- Binding: Paperback
- 248 pages
Review
This guide offers an easy and effective way to learn how to apply the earned value management technique to real world projects using Microsoft Project. The EVM tool included brings a coherent framework that can be used on any project. I highly recommend this book. --Kesary Vanaja, Project Manager, HCL Technologies Ltd.
Those planning to use or currently using Microsoft Project will find this guide and software to be a valuable resource for managing their projects. The examples, tips, and illustrations are very good. It is an amazing work! --Hari Prasad, PMP, CQM, Senior Process Manager, MphasiS, An EDS Company
About the Author
Sham Dayal, PMP, has over 13 years of practical experience in the IT industry where he specializes in managing projects using EVM techniques with Microsoft Project software. Mr. Dayal currently holds a program management position with MphasiS, a global IT services firm, and is co-founder of Connoizor Software Pvt Ltd, a company that specializes in software tools and templates, project execution, and product development. He was the first person at MphasiS to successfully implement EVM for project tracking (progress, status and forecasting) and was instrumental in creating a new technique for tracking the progress of production support projects. This new technique, based on the EVM concept, won a Quality Knowledge Excellence Award. Mr. Dayal is a frequent speaker on EVM and has been published in leading journals on EVM pertaining to more effective project lifecycle management. He has a bachelor's degree in Computer Science and a master's in Applied Statistics.
Most helpful customer reviews
5 of 5 people found the following review helpful.
Inaccurate, imprecise and unsophisticated
By J. Baber
If you want a book that teaches you about Earned Value Project Management then, don't buy this book. I will not list everything wrong with this book due to space limitations. I am searching for a book that can be used in my EVMS class. I will not require students to purchase a book such as this one which is full of errors.
The title alone is enough to make anyone suspicious. A book that states it will show the reader how EVM can be used on "Any Size Project Effectively" is a grandiose and delusional claim. I am sure the next Western Power that wants to build a Multi-billion dollar naval ship will all be clamoring to purchase the $99 Excel spreadsheet offered on the accompanying CD to run their next project.
The author is completely confused by stating on page x that the PMI Practice standard is" now the accepted EVM standard for the ANSI." This statement is factually incorrect and one I am sure the NDIA PMSC (custodians of the ANSI/EIA-748) would be surprised to learn. On page xvi the author states that "After reading chapter 3, you will understand the entire EVM technique. . ." After reading chapter 3, I discovered that statement was false and realized the author is severely uninformed regarding the use of Earned Value Management. So let's focus on chapter three.
First, it is absolutely amazing what is not included in this chapter. There is no discussion of the Control Accounts, Work Packages or Planning Packages. I am convinced the author does not understand these key and foundational artifacts of EVMS. This chapter, which is supposed to explain "the EVM technique" completely lacks sophistication and accurate detail. For example, on pages 22-23 he only explains two EVM measures for tasks/work packages (%Complete and 50/50) and then states the 50/50 "method is not recommended." This poor, erroneous and narrow recommendation for EVMS task/work package measurement is a very good reason to forgo purchasing this book. One last example from chapter 4, but which is also present in chapter 3 is a very key point. On page 60 is figure 4.1. This figure is awash with fundamental EVMS errors. First, there are several zero budget tasks and one of the zero budget tasks has a negative VAC. Second there are numerous tasks shown where the BCWP (Earned Value) exceeds the BCWS (Planned Value). This is possible if the figures were only monthly and there was more BCWP to earn in the out months, but that is extending a level of sophistication that is absent in this book. It is safe to assume this figure is incorrect and misleading as printed. As I stated above there are many, many more problems that could be described.
This book was provided by the publisher as an instructor review copy. This company (J. Ross Publishing) has one of the most unfriendly policies in this regard which is: Return this book in a saleable condition in 45 days or pay full market price. The only exception being that if the book is adopted in a course, then you pay nothing. Needless to say I will not be adopting this poorly written and inaccurate book.
The good news, well sort of. It is clear this author is grossly uninformed in regard to EVMS, but he does provide some useful guidance on Microsoft Project set-up and tips. The MS Project set-up and tips are of no use to the unskilled EVMS analyst and some tips and suggestions may lead you astray. However, no revision of this book is likely to correct all the EVMS problems and the fact that MS Project 2003 is the version demonstrated throughout does not help. Even if it were updated to MS Project 2010, it would not correct all the EVMS misstatements. If this author were to partner with a knowledgeable EVMS person then there exists the chance for a very good and useful book.
I have written other book reviews on EVMS books which you can also read.
11 of 11 people found the following review helpful.
in one word: Disappointing
By Leonardo Abeles
I purchased this book when it was pre-released hoping to find innovative solution for EVM based on microsoft project 2007. Even though released in 2008 the book focuses on MS project 2003 and not 2007. None of the visual reports nor additional features of MS project 2007 are there.
The book is extremely expensive and doesn't give the value for the money.
It contains a CD with a commercial excel sheet for earned value and it focuses on how to use it instead of describing solely what is meant to be, a MS project guide of implementing EVM.
I got the impression that this book is all about advertising for that excel sheet and nothing more.
In short, it was a huge miss of it's target.
A big dissapointment.
3 of 3 people found the following review helpful.
YAPAC Book - Yet Another Point And Click - Misleading and Fairly Useless
By Wildman Hilljerk
Avoid this book like the plague. Sad to say that it only took about 15 minutes reviewing parts of the book to determine that for the most part it's simply what I term a YAPAC book - "Yet Another Point and Click" book.
The author devotes a lot of time to laboriously walking through how to navigate MS Project - point here, click there - when this information is readily available on Internet sites too numerous to mention. This is absoluteldy not value added content in a thin volume that lists for over $70 US.
Next we see what on the surface are some time based equations for schedule measurement in which the author presents some interesting, but laborious, equations that take a long path to provide the same data available with fundamental EVM equations. Is the author not familiar with the Project Management Institute's "Practice Standard for Earned Value Management"? Surely anyone with the PMP designation writing a book would be. There's no mention of those who have done legitimate work on time based measurements, but the author leads us to believe that his (erroneous) calculations for time based measurements are his original ideas.
The techniques the author presents for measuring and reporting based on EVM show a lack of the in-depth understanding of MS Project necessary to apply it effectively. Those well versed in MS Project know and realize the software's notorious inconsistencies in providing accurate tracking and calculation of EVM, and the problems related to task versus resource planning. The author blissfully ambles along taking things at face value without acknowledging any problems whatsoever, and in fact recommends techniques that virtually guarantee poor metrics and results.
And what's up with this spreadsheet thing? Why on earth would I want to be enticed to pay big money for what, after all, is a spreadsheet that I could create and tailor in an evening to do exactly what I want? I immediately lost all interest in discussion of this "tool" when the references to "copy and paste" and manual entry of data came into play. A true tool with any sophistication would simply create the spreadsheet for me, or populate a template, or do something besides require me to move data from one program to another. Perhaps I could recommend a good book on Visual Basic for Applications (VBA) and its power to the author and his colleagues. The CD that comes with the book says you get a 6 month license to use the "tool". This is a joke, right?
As one who also holds the PMP certification, a graduate degree in project management, and years of experience in project management, teaching and developing courses on EVM, and having written research works on the topic, I can state that I have a solid and firm basis for offering the above critiques. Looking at this book just motivates me to write one that provides true value on the topic . . . and at a modest cost.
Earned Value Management Using Microsoft Office Project: A Guide for Managing Any Size Project Effectively, by Sham Dayal PDF
Earned Value Management Using Microsoft Office Project: A Guide for Managing Any Size Project Effectively, by Sham Dayal EPub
Earned Value Management Using Microsoft Office Project: A Guide for Managing Any Size Project Effectively, by Sham Dayal Doc
Earned Value Management Using Microsoft Office Project: A Guide for Managing Any Size Project Effectively, by Sham Dayal iBooks
Earned Value Management Using Microsoft Office Project: A Guide for Managing Any Size Project Effectively, by Sham Dayal rtf
Earned Value Management Using Microsoft Office Project: A Guide for Managing Any Size Project Effectively, by Sham Dayal Mobipocket
Earned Value Management Using Microsoft Office Project: A Guide for Managing Any Size Project Effectively, by Sham Dayal Kindle
Tidak ada komentar:
Posting Komentar